Route 4 Paving Update….

Just to keep everyone in the loop…

The City’s contractor is near completion of the concrete repairs to curbs, sidewalks, drive aprons and handicap ramps along Verity Parkway (State Route 4/73) between Girard Avenue and Tytus Avenue ahead of the planned resurfacing. 

ODOT will manage the paving portion of the project.   ODOT’s contractor is scheduled to mill the existing asphalt and pave in September.  This project is part of ODOT’s Urban Paving Program which partially funds paving of State Routes through municipal corporations.   The total project cost for the concrete repairs and paving is $970,000.  The City’s share is $495,000.    

 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s